Audit Dept flags continued delays, RM514m in unauthorised variation orders on Sabah Pan Borneo Highway
KUALA LUMPUR, Oct 5 — A total of 10 work packages for the Sarawak Pan Borneo Highway (LPB) project have been fully...
Entities › name
3 headlines · 2 outlets · 2026-10-05 → 2026-10-05 · Wikipedia ↗ · 🔒 Follow
KUALA LUMPUR, Oct 5 — A total of 10 work packages for the Sarawak Pan Borneo Highway (LPB) project have been fully...
KUALA LUMPUR: Only four of 35 work packages under Phase 1 of the Sabah Pan Borneo Highway (LPB) project have been completed since its inception in 2015.
KUALA LUMPUR: Only four of 35 work packages under Phase 1 of the Sabah Pan Borneo Highway (LPB) project have been completed since its inception in 2015.